by Coba | Jun 13, 2019 | The Linnea
It’s full-steam ahead at our 11th Street Corridor condominium project, The Linnea. MEP (mechanical, electrical, and plumbing) is well underway and resilient channels have been installed. Resilient channels, one of the most efficient methods of sound reduction,...
by Coba | May 13, 2019 | The Linnea
Now that we’ve installed the new roof on our 11th Street Corridor condominium, The Linnea, we can begin preparing the space for its future use: outdoor living space across two private roof decks accompanied by a green roof! But first, we tackle proper drainage....
by Coba | May 1, 2019 | The Linnea
The basement slab is poured. The roof is installed. Duct work and plumbing rough-in are under way. Framing is near completion. We’ve hit quite a productive groove at The Linnea, our 11th Street Corridor, 11-unit condo! Excited to see what we’re working...
by Coba | Apr 4, 2019 | The Linnea
We are framing out eleven units for our Columbia Heights luxury condo, The Linnea. When complete we will have three one-bedroom units, nine two-bedroom units (two of which will have private roof decks) and one three-bedroom unit. The property website — including...
by Coba | Mar 15, 2019 | The Linnea
Our Columbia Heights condo project, The Linnea, is in framing. This is one of our favorite parts of the project as we can really start to see the units come to life!
by Coba | Oct 11, 2018 | The Linnea
Our purpose is not only to create inspiring, functional, luxury living, it is also to construct with absolute integrity. It is imperative to us that we utilize methods and materials that will ensure the longevity of the structure. To that end, we have completed the...